Naam auteur: goudkantoor

Ruby Creek Dec 2020

Dear Clients I am very pleased to report that today, our long awaited CIP processing plant started.Commissioning of the various components within the new plant have finally begun. Our Tailings Storage Facility (TSF) is now complete, and our CIP processing plant support buildingsare completed with installation of components like laboratory equipment nearing completion as well.

Ruby Creek Dec 2020 Read More »

Transeco Dec 2020

Good Day Clients! After a long year battling COVID-19 restrictions and recently overcoming the challenges the rainy season brings, I am happy to report that we have managed to restart production. As previously reported, our processing plant required repairs and modification, along with further optimization which are crucial to reach its maximum output. I am

Transeco Dec 2020 Read More »

Ruby Creek Okt 2020

Dear ClientsWe continue to hope you are all safe during these global troubling.Following on our last update, I report that our work progresses but unfortunately not at the speed wehad hoped. We had encountered a delay in completing the construction and connection to the nationalpower grid. Our TSF is almost completed and our CIP processing

Ruby Creek Okt 2020 Read More »

Transeco Okt 2020

Good Day Clients! After a long eight months, the Ghanaian borders have opened, and I am thrilled to be finally writing to you from Ghana. I can confirm the team continue to operate on minimum staffing levels due to Government COVID-19 restrictions. The pandemic further affects land and sea borders with the ports in Ghana

Transeco Okt 2020 Read More »

Transeco Sep 2020

Dear Clients We hope you are all keeping safe and well during these troubling times. Transeco are pleased to inform clients that we have successfully started to fulfill gold contracts since the beginning of July, this is a gradual process, but we are optimistic the pace will grow with production. Following on from our previous

Transeco Sep 2020 Read More »

Ruby Creek Aug 2020

Dear ClientsWe hope you are all safe during these troubling times with this virus still very much upon us.Finally, your long awaited update and I am proud to report to you on the present status on our Gold Hill Mine development. And our next big milestone of trial production is finally approaching, we are so

Ruby Creek Aug 2020 Read More »

Ruby Creek Aug 2020

Het heeft even geduurd, maar 300 ton erts per dag was het doel om door de CIP plant te laten verwerken en dat lijkt nu waarheid te worden. De grote pomp die door de Covid19 lockdown in Zuid Afrika was blijvenstaan is nu in Tanzania aangekomen. Dit betekent dat de begin productiecapaciteit van 300 ton

Ruby Creek Aug 2020 Read More »

Ruby Creek Juni 2020

Via Marc van Daalen (Goudkorting) hebben wij de volgende informatie mogen ontvangen op persoonlijke titel. Wij kiezen er voor deze informatie beschikbaar te maken voor u, daar wij zelf niet instaat worden gesteld om met de heer Slavik te communiceren. Ik (Marc van Daalen,) heb gisteren een lange tijd met Rob Slavik van Ruby Creek Resources

Ruby Creek Juni 2020 Read More »

Scroll naar boven

We gebruiken cookies om jouw ervaring te verbeteren.

Onze website maakt gebruik van cookies om je surfervaring te optimaliseren. Door verder te gaan op onze website, ga je akkoord met het gebruik van cookies.